Project
  1. Planning / Project setup
  2. Business
  3. Development
  4. Validation
  5. Release
Done
EdgeLink Controller1 day left
  1. Jul 29Aug 02
  2. Aug 05Aug 13
  3. Aug 14Sep 27
  4. Sep 30Oct 25
  5. Oct 28Nov 08
12%
Aurora Platform2 days left
  1. Jul 22Jul 30
  2. Jul 31Aug 14
  3. Aug 15Sep 13
  4. Sep 16Oct 04
  5. Oct 07Oct 18
18%
Insight Engine4 days left
  1. Aug 05Aug 16
  2. Aug 19Sep 06
  3. Sep 09Oct 18
  4. Oct 21Nov 15
  5. Nov 18Nov 29
3%
Pulse Firmware6 days left
  1. Apr 01Apr 12
  2. Apr 15May 10
  3. May 13Jul 05
  4. Jul 08Aug 02
  5. Aug 05Aug 18
95%
Nebula Services8 days left
  1. Jun 10Jun 21
  2. Jun 24Jul 12
  3. Jul 15Aug 20
  4. Aug 21Sep 13
  5. Sep 16Sep 24
40%
DataForge12 days left
  1. Apr 08Apr 19
  2. Apr 22May 17
  3. May 20Jul 19
  4. Jul 22Aug 24
  5. Aug 26Sep 06
72%